Installation of ACE platform on Azeri-Chirag-Gunashli block expected in 2Q2023

Tokyo, 10 April, /AJMEDIA/

Installation of the Azeri-Central-East (ACE) platform on the Azeri-Chirag-Gunashli block is expected in the second quarter of 2023, AJMEDIA reports via the BP.

The platform’s construction progress is 99 percent complete, and work is underway for testing and preparing it for launch.

Testing of the new BP platform is 95 percent complete. As many as 1,500 specialists, 90 percent of whom were Azerbaijanis, took part in the construction of ACE.

In addition, the construction of a 14-kilometer pipeline has been completed, and three subsea structures have been installed. There are also some achievements in connecting export pipelines from the ACE platform to the Sangachal pipeline. The connection of the gas pipeline has already been completed, and the oil pipeline is expected to be connected by the end of the second quarter of this year.